urbe water lifting plant - roma nord purifier
TEATEK WATER
YEAR: 2020
PROJECT: IN PROGRESS
CUSTOMER: ACEA ATO 2
LOCATION: ROME
Design, construction and installation of a
QGBT with 4000A switches
Softstarter switchboard
User distribution panel managed by REDUNDANT PLC
PLANT DESIGN
– calculation report
– electrical relationship
– lighting calculation for internal and external rooms
– MV substation and control room plans
– cable ducts.
REALIZATION
– QGBT with 4000A switches with 8 630KW Soft Starter Starters for Augers
– Pump panel with 5 160KW Soft Starter Starters
– Group network exchange framework
– Redundant Siemens 1500 PLC panel for plant automation and remote control
– Internal and external lighting and power plant distribution panel
– Replacement of the 4 1250 KVA transformers
ELECTRICAL PANELS
PRELIMINARY WORKS
Teatek S.P.A.
REGISTERED OFFICE
NAPOLI Via S. Lucia 36 - 80132
OPERATIONALS OFFICES
NAPOLI: Via Maddaloni snc c/o Consorzio 'AREA' - 80011 ACERRA
ROMA: Contrada Piombinara snc - 00034 COLLEFERRO
MILANO*: Via Polveriera 25 - 20026 NOVATE MILANESE
*LOCATION NOT SUBJECT TO ISO VERIFICATION
teatek@adpec.it
+39 08118919610
P.IVA 06362981216