Design, construction and installation of the electrical panel for the inverter management of the Bosco ferentano degasser, construction of a Point-to-Point with PLC and Radio Modem

Electrical scheme design.
Electrical panel construction with six inverter starts for 16kW pumps to relaunch the tank, 4 Inverter starts for 3Kw blowers, system distribution.
Construction of electrical system and driving force of the site.
Lighting system inside and outside the switchboard room. Creation of a PLC panel for the automation of the entire system. Realization of an electrical panel Supply point