BOSCO FERENTANO DEGASSER

Year: 2020

Customer: ACEA

Plant: CIAMPINO (ROME)

 

Design, construction and installation of the electrical panel for the inverter management of the Bosco ferentano degasser, construction of a Point-to-Point with PLC and Radio Modem

Electrical scheme design.
Electrical panel construction with six inverter starts for 16kW pumps to relaunch the tank, 4 Inverter starts for 3Kw blowers, system distribution.
Construction of electrical system and driving force of the site.
Lighting system inside and outside the switchboard room. Creation of a PLC panel for the automation of the entire system. Realization of an electrical panel Supply point

Teatek srl

Via Maddaloni snc
c/o Consorzio 'AREA'
Acerra - 80011
NAPOLI - ITALY

info@teatek.it

+39 08118919610

P.IVA 06362981216

Leave a message

PRIVACY

6 + 15 =